Kingpost
Rabun Builders

Draw schedule

Funded, submitted, and upcoming draws, with the key dates beside them, so a call becomes a glance.

Laurel Point

Funded to date $3,280,000 of $4,100,000

Open build
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
Funded
4
Dry-in complete
Roof, windows, and exterior doors set
Funded
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
Funded
6
Drywall and interior trim
Drywall hung and trim complete
Funded
7
Cabinets and finishes
Cabinets, counters, and flooring installed
8
Final and closeout
Final inspection and punch list complete
Upcoming

Key dates

  1. Final inspection
    August 25, 2026
    Inspection
  2. Closing walkthrough
    September 6, 2026
    Closing

Cherokee Point

Funded to date $2,044,000 of $3,650,000

Open build
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
Funded
4
Dry-in complete
Roof, windows, and exterior doors set
Funded
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
6
Drywall and interior trim
Drywall hung and trim started
Upcoming
7
Cabinets and finishes
Cabinets, counters, and flooring installed
Upcoming
8
Final and closeout
Final inspection and punch list complete
Upcoming

Key dates

  1. Rough-in inspection
    July 18, 2026
    Inspection
  2. Cabinets delivered
    August 6, 2026
    Delivery
  3. Move-in walkthrough
    December 13, 2026
    Closing

Timpson Cove

Funded to date $713,000 of $2,850,000

Open build
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
Funded
3
Framing complete
Framing and roof deck complete
4
Dry-in complete
Roof, windows, and exterior doors set
Upcoming
5
Mechanical rough-ins
Plumbing, electrical, and HVAC rough-in passed
Upcoming
6
Finishes and closeout
Interior finishes and punch list complete
Upcoming

Key dates

  1. Framing complete
    July 22, 2026
    Milestone
  2. Framing inspection
    July 25, 2026
    Inspection
  3. Windows delivered
    August 9, 2026
    Delivery

Wildcat Ridge

Funded to date $230,000 of $2,300,000

Open build
1
Permits and mobilization
Permits pulled, site mobilized
Funded
2
Foundation complete
Foundation poured and inspected
3
Framing complete
Framing and roof deck complete
Upcoming
4
Dry-in complete
Roof, windows, and exterior doors set
Upcoming

Key dates

  1. Foundation inspection
    July 19, 2026
    Inspection
  2. Framing starts
    July 30, 2026
    Milestone