Lake Burton · Interior rough-in
Cherokee Point
148 Cherokee Point Rd, Clayton
$3,650,000
Contract price
52% complete
The client's window

Sarah checks Cherokee Point every morning at 7:12 AM from Buckhead, Atlanta.

Caught up as of the last 7:12 AM check.

Progress photos

1 day ago
Interior rough-in
Posted by Dale WhitfieldJuly 15, 2026 · 4:30 PM

Electrical rough-in wrapped on the main floor and the tubs are set upstairs. Rough inspection is booked for Thursday.

Main floor panel and home runs
Primary bath tub set
Great room ceiling wiring
Plumbing rough-in
Posted by Dale WhitfieldJuly 13, 2026 · 3:10 PM

Water lines are run and the kitchen island rough is in the slab. Everything pressure tested and holding overnight.

Kitchen island rough
Manifold and supply lines
Dry-in
Posted by Kurt CannonJuly 10, 2026 · 11:40 AM

The house is dried in. Roof is on, windows are set, and the lake wall is all glass now. Come stand in the great room on your next visit.

Lake wall glazed
Standing seam roof
Front elevation
Framing
Posted by Dale WhitfieldJuly 4, 2026 · 9:20 AM

Framing topped out. The second floor is decked and the great room trusses flew this morning.

Great room trusses
Second floor deck

Decisions waiting on you

Primary Bath
Due in 3 days
Floor and shower tile

Honed Carrara 12x24 on the floor, stacked 3x9 on the shower walls, matte finish.

Selection $15,200
Great Room
Upcoming
Light fixtures

Two forged-iron chandeliers over the great room with sconces flanking the fireplace.

Selection $9,400

On the record

Appliance packageApproved
Sarah Harlan · July 8, 2026
CO-002 · Screened porch fireplaceApproved
Tom Harlan · July 1, 2026

Draw schedule

View all
1
Permits and mobilization
$365,000
Funded
2
Foundation complete
$548,000
Funded
3
Framing complete
$620,000
Funded
4
Dry-in complete
$511,000
Funded
5
Mechanical rough-ins
$475,000
Submitted to the bank
6
Drywall and interior trim
$438,000
Upcoming
7
Cabinets and finishes
$401,000
Upcoming
8
Final and closeout
$292,000
Upcoming

Key dates

Dry-in complete
July 10, 2026
Done
Rough-in inspection
July 18, 2026
Inspection
Cabinets delivered
August 6, 2026
Delivery
Move-in walkthrough
December 13, 2026
Closing