Lake Burton · Framing
Timpson Cove
451 Timpson Cove Rd, Lakemont
$2,850,000
Contract price
34% complete
The client's window

Daniel and Mia Reyes last opened this build 2 days ago, from Charlotte, NC.

Progress photos

4 days ago
Framing
Posted by Dale WhitfieldJuly 12, 2026 · 11:00 AM

First floor walls are standing and the deck framing steps down to the water just like the plan.

First floor walls up
Stepped deck framing
Foundation
Posted by Kurt CannonJuly 5, 2026 · 2:30 PM

Foundation is poured and cured and the slab is on grade. Framing lumber is stocked and starts Monday.

Foundation walls
Slab on grade

Decisions waiting on you

Exterior
Was due 2 days ago
Stone and siding

Tennessee fieldstone on the water elevation, board and batten above, dark bronze windows.

Selection $71,500
CO-001
+$12,800
Boathouse roof to match the main house

Change the boathouse roof from asphalt shingle to standing seam to match the main house.

On the record

Roof colorApproved
Mia Reyes · July 1, 2026

Draw schedule

View all
1
Permits and mobilization
$285,000
Funded
2
Foundation complete
$428,000
Funded
3
Framing complete
$456,000
Submitted to the bank
4
Dry-in complete
$399,000
Upcoming
5
Mechanical rough-ins
$370,000
Upcoming
6
Finishes and closeout
$342,000
Upcoming

Key dates

Framing complete
July 22, 2026
Milestone
Framing inspection
July 25, 2026
Inspection
Windows delivered
August 9, 2026
Delivery